Thursday, April 7, 2016

4-5-16

Controlling Operation: Layout Staking Phase 1A
Workable 10/8
Hi 52         Lo 34
Weather Mostly Sunny, Breezy

Woodruff worked on waterline at Marion and Bartlett.
Indiana Earth worked on Removals on Riverside.
JPR worked on Layouts 
A weekly progress meeting was held see minutes below

4-5-16 Progress Meeting
                Started with Introduction
                Then Reith Riley was to introduce an updated schedule.
Reith Riley did not give an updated schedule, the reasoning was they did not have the submittal back for structure 802, or rim elevations for Chippewa or Marion. They also noted the lack of a permit for getting into the River. They proceeded to give an oral presentation. They will be working at Marion and Michigan moving the water 20” waterline which is anticipated to take the rest of the week. They will be working on removals on Bartlett from Riverside to Saint Joe this week. They plan on working on Michigan Street north of Bartlett to Angela Boulevard, on the intersections pedestrian ramps, working on the east side first and then moving to the west side. 
                Utilities
AEP Bob Strasburg:  AEP will be out today to remove the light poles on Bartlett from Riverside to Saint Joe. Which is a week later than scheduled. They will then work on the line down the alley east of Michigan next week, and should take a day to set temp pole.
AEP Tony Macias gave an update on the Chippewa intersection and it was stressed that he be done with his work before the first of June. He also filled us in that the Windstream line was on Main Street not Michigan as originally thought.
Nipsco will be done with the Bartlett street intersection by April 15th.
Comcast did not attend, but Jay Castello did email stating, I’ll run by today to see if the R/W is staked and probably wait till the trees have been removed before I bury the new line. At Chippewa I’ll check with my contractor to see when they will start and let you know. On Main north of Chippewa the underground was installed yesterday and hoping to have the service removed from an old transmission pole for the project. I’ll keep you posted with updates.
US Signal did not attend.
                Utility Upgrades
AEP/Robert Henry gave a brief time frame on the work and how it is progressing. The work at South Street is complete. They have moved to Main and are working from Columbus Court to Jefferson St. and this work should be completed by the 18th. They will then move south from there.
Nipsco/ Phil Griffin: while working on the Nipsco upgrades downtown they ran into a vault on Main St. North of Colfax to the alley. The vault goes all the way out to the curb line.
                Took break and utilities and businesses left at this time
                Additional RW
Division A
1.       Cavalry Temple –sign under negotiation
2.       Palmer Funeral Home - agreed
3.       XB Real Estate-closure need
4.       Sandra V Case – available on May 21st
                Division B
1.       First Source-paying Tuesday
2.       Fifth Third bank-
3.       QDI Realty- pay Tuesday
4.       Memorial Hospital Parcels 1, 2 & 3- closed last week
5.       Transpo- recorded
6.       Billboard Burkhart

Submittals Division A
Martell 1 item 177 & 232 are still out was due 3-25-16
 Reith Riley 4 missing storm and casting due -4-6-16
                Submittals Division B
Woodruff 1 Structure 802 due 3-23-16 Roger called Reith Riley had it by the end of the meeting.
All other submittals at this time in good standing.
Reith Riley still needs rim elevations for Marion and Chippewa. Roger called and Marion was given to Reith Riley before the end of the meeting.
                Reith Riley Construction Concerns
Was wanting more information on the vacuum line running out of the hospital east down Marion and the vacuum line running to MAR Main.
Joint lay out for Main by Bronson will be State standard.
They asked about the duct bank on Michigan by Madison at the current location and it should be out of the way.
Reith Riley needs to send a letter to the City and then the City will request a waiver
 from the DNR to work in the River.
Tanner asked about the permits and occupancy bond. He was having trouble getting them from the City Toy looked into it during the meeting and the fee will be waived.
Reith Riley was having trouble with residence parking on Bartlett after it had been closed.
                City Concerns
Field office is still not ready to move in.
Railroad Insurance- Reith Riley needs to get for Michigan St. and I need to get a precon scheduled with the Railroad.
Video Camera’s for the downtown area: Corbitt is going to review  the option of placing them on the buildings verse poles.
The next progress meeting will be 4-15-16 at 9:00 AM

 