Fraction of day workable 10/10
Hi 54 Lo 42
Weather AM Cloudy PM Cloudy
Indiana Earth worked on grading out Bartlett between Michigan and Saint Joe.Indiana Earth had to lower a gas service that was in the realigned Bartlett's subgrade.
Woodruff worked on storm sewer west of Michigan on Bartlett.At approximately 3:15 p.m. we were notified that the hospital parking lot did not have power, we discovered that one of the conduits Woodruff cut actually did have wires in it. Pemberton Davis was on site to make the repair.
The weekly progress meeting was held today. See meetings posted below.
Had a meeting at the City with an update on the AEP work that will be taking place on Michigan Street. between Western and Colfax.
Went and looked to see if there is a vault under the Chase tower building.
Met with the Manager of MacDonalds Tony Yado.
Meeting With:
|
|
Meeting Date:
|
|
Regarding:
|
Progress Meeting
|
Construction and
Utilities
|
ITEMS TO BE
DISCUSSED
9:00 AM Introductions/Sign
in
The Weeks up Coming
Events/Schedule
Reith Riley will start working on Division A at Chippewa and
Main St. They will have the far right lane closed on Main St. at that
intersection.
Division B they work on removing the Mar Main pharmacy and
build the temporary road from Michigan to Marion. At Bartlett Street they will
work on curb and pavement between Saint Joe and Michigan. They will also work
on structures west of Michigan.
Utility Relocation Issues:
AEP:
Bartlett Street: AEP will set back some street lights on Bartlett
Street, all other work on Bartlett is complete. On Marion Street the pole
relocation east of Michigan has been completed. When this work was done it blackened
the east side of Michigan between Marion and Navarro. At Chippewa the
Transmission Line running east and west is still not relocated. Tony Marcia
anticipated AEP will start working on this area in another week and should be
done by the end of May.
Robert Henry: is working at Wayne and Main
St. They are 4 days ahead of schedule.
NIPSCO: Will be bringing in a third
crew and the will start working from Lassalle to Madison on Main St. The City
is still concern about the crossing at Colfax and Main.
Comcast: We’ve completed Bartlett, hope to have
the city permit soon and start Chippewa next week. I believe Rogers question
about the progress down town was answered by Rick Walstra last week! Thanks
US Signal: Has the Engineering work
completed on Chippewa Street and is working on getting the permits. They will
then get started. US Signal will be responsible to move the Windstream cable
that is bundled with its cables located on the East side of Michigan.
Windstream on Main Street is taken care
of. On Michigan Us Signal will be handled the relocation.
AT&T: Did not show up. They still
have the issue at the ally on Bartlett street just west of Michigan. A new
issue arose with the AT& T vault on the North West corner of Bartlett and
Michigan. A meeting will be set up to meet with AT&T, Reith Riley, JPR and
the City.
Water Dept. was unable to attend. They
called and had no issues.
Additional RW and Encroachments:
Division A
1.
Cavalry
Temple
2.
Palmer
Funeral- Home, closed yesterday, Asbestos inspection can take place later
next week.
3.
XB
Real Estate-is clear
4.
Sandra
V Case- City will move out on May 17th, can get asbestos testing on May
18th get officially May 22nd.
Division B
1.
First
Source-property cleared
2.
Fifth
Third bank-Pay Voucher on the 17th.
3.
QDI
Realty- property Cleared
4.
Memorial
Hospital Parcels 1, 2 & 3- the City has right of entry
5.
Burkhart
sign- The sign will either be removed by Burkhart or by Reith Riley by the
17th of May. I will contact Bob Strasberg about getting the power disconnected
to the sign.
Submittals (List
at Meeting):
Action Items
1 QC/QA concrete-
Reith Riley needs to get new price to the City.
2 QC/QA HMA- Reith
Riley needs to get new price to the City
3 RFI # 4 Blocks-
The city is meeting on this topic Monday
4 Permit to
enter River/cofferdam- Has been received and Reith riley can enter the
River to do the work from May 2nd to May 13th.
5 Asbestos at
Mar Main removals by Memorial Hospital Subcontractor. This work has been
completed and a letter will be forwarded confirming this.
6 Sign for office-
Pemberton Davis is having the graphics main and ill place it next week.
7 Placement of
Message boards for Marion and Bartlett- Corbitt requested the signs at Park
and Angela be moved for better sight distance. He also wants the sign North of
Lassalle moved to the parking area at Lassalle and Michigan.
8 Drive for
Hospital work trailer building on Bartlett- received the revision
yesterday.
9 Chase Tower (Main
Street) The City will investigate a possible vault out under the sidewalk
Reith Riley Construction
Concerns/Questions:
City
Concerns/Questions: Corbett asked about the Video Cameras that need to be
placed. Martel is going to meet with the City Monday.
Corbett informed Reith Riley to wait on working on South
Street and Michigan and South and Main as long as they can. The removal of the
signs may not happen. They need to proceed per plan on all other locations.
Next weekly progress meeting 5-6-15