Progress Meeting Min 3-25-16
Introductions
Schedule
Up Coming Schedule- Reith Riley will start working on
Riverside on April 4th. They will start the street scape area
downtown around April 21st.
Utility Issues
Nipsco
will be at Colfax and Main for 2 to 3 weeks. They will be working from Lassalle
to Colfax should be done by mid-April, Lassalle North should be done by May 7th.
InfraSourse is supposed to have a schedule to Nipsco by the end of the day.
AEP
will remove the poles on Bartlett next week from Riverside to Saint Joe Street.
Then work on the temporary feed at the ally between Saint Joe and Michigan.
Comcast
had no hard date on the work at Bartlett or the work at Chippewa.
AT&T
i called Denis Bunch after the meeting and he plans on having the line at
Bartlett moved ASAP
US
Signal and Windstream at Chippewa was discussed and contact information for
Windstream was not known by anyone.
The city will be working on Main Street from Madison to
Marion Street next week trying to locate electric duct banks. They city
requested Reith Riley to lay out structures in the area to help make sure the
Duct banks and sewer lines are not in conflict.
Additional
R/w and Encroachments Marmain is complete, Palmer funeral hope to be signed and
done in 30 days, Chase bank by the End of May, Cavalry Temple still negotiating
, 5th /3rd Bank still under discussion.
Submittals
Reith Riley requested that when submittals are signed by the designer and more
than one designer is involved they do not receive the approval until all three
sign off. Roger called JPR was called due to the structures not being completed
yet. The Temporary Panel Signs were also discussed that a plan change would
have to be made. Reith Riley asked about Rim elevations not being on all the
plans. They also requested the CAD files for all the plans so it can be used
for layout.
Web Cameras Reith Riley is working
on getting the camers and getting them placed. The cost of providing the
cameras is on Reith Riley, if the City decides to keep the cameras when the
work is done then they will buy them.
Videoing the Street will be done
by a hired company. If the Video work is not done before Reith Riley Starts
doing any construction work then Reith Riley will video the area they are
working in themselves.
Construction
Sinage: temporary RCA signs will be placed next week. Message board signs will
be placed next week on Riverside and Bartlett informing of the closure.
City Concerns: Possible paving by Xavier
School prior to the start of the school in August. Ground breaking will be
coordinated with the Mayor’s office. The location of the field office was
discussed and the use of a building instead of a trail. This will have to be
run by Eric.
No comments: