Thursday March 10, 2016

A DTSB RAS meeting was held at 8:00 am at the down town library. Corbitt introduced Toy Villa, Roger Nawrot and myself. He gave a brief overview of the Two-way conversion and role everyone would play.

A utility relocation precon was held at 1:00 pm at the South Bend Street Department. See meeting min below.

Utility Pre-Construction Meeting Minutes

March 10, 2016
The utility preconstruction meeting started out with a brief overview of the limits of the project, from Angela Blvd to Chippewa Ave on Main Street and Michigan Street. There are roundabouts at Bartlett St. Marion St. and Chippewa Ave. The time frame at which the project would take place Reith Riley would like to get started the last week of March or the first week of April. The intersections of Bartlett St and Marion can closed be from May 7th to Sept 7th and Chippewa can be closed from June 6th to Aug 5th.
Then introductions were then made: (see attached sign in sheet)

Rieth Riley comments:

Rieth Riley then gave a brief over view:  Anticipate starting work the last week of March/first week of April.  They will be having 5 crews working simultaneously.  Crews will be working at Bartlett, Marion, Chippewa, the Railroad underpass and a crew working on Street scape.  Rieth Riley’s schedule is first starting on the south end at Main and Chippewa doing the west side of Main at Chippewa. On the North end they will be starting the storm sewer at the river and working on Riverside on the East side of Michigan Rd St. At Marion St Water main relocation is the first priority. On Main St and Michigan from Lassalle to Ewing Rieth Riley will be working the west side of both streets first.     

AEP Comments:
Talked about the open cut conduit that was going to be placed on Main Street from South St. to Columbus St. and on Michigan St. south of Bartlett to Marion and west on Marion to just short of Lafayette St. AEP has over 30 work orders they plan on starting around March 14th and Finishing around mid-June. Rieth Riley noted the AEP work in the contract and the open cuts are not mentioned in the contract. When Bartlett St. closes AEP will have a lot of work in that area to do, which will have to be done when the road is closed. 
Corbitt explained that there are two parts to the utility work. One portion of the utility work that is required is to get the job done and part two the utility work that the utilities would like to get done in concurrence with the work being conducted by Reith-Riley.  Marion roundabout is the case were relocation and upgrade is getting done together. Some network upgrade that needs to be done is separate from the two-way project.  Reith Riley really needs to see a breakdown on were all this work really is so they can work it into their schedule.  Corbitt asked AEP to get Reith Riley a set of plans regarding the network upgrade.
Back to AEP
AEP would like to have a meeting with Reith Riley separately so they can go over the work and time frame so they are not in the way and are flexible with what they can do.  Some of the relocations have to be completed before Rieth Riley can start work will.  One transformer has been relocated already and the other one will be removed tomorrow and moved. Demolishing of the old facilities will begin and be filled in.  When open cuts across the roads are being performed Michigan
Page2
and Main Street will only be closed down to two lanes. The side streets will be closed down but only one at a time. The Network upgrade will start at Michigan and Navarre on 3/11/16 and that will coinside with Michigan and Bartlett but we are really flexible if we are needed to get out of the way. We can tear down and set up in no time. 
 The overhead line on Chippewa running East to West will be pushed underground and the overhead line will be eliminated.
The Bartlet St. underground lines are already in, the overhead lines  that run down the alley to the east  will be a couple step process that will be another 3 to 4 weeks. 
AEP has a job that is scheduled for Monday waiting on permit. The job is in conjunction with the upgrades for the contract. AEP needs a permit for that work from the city. The city needs the MOU before permit will be issued.  If it is outside the construction area permit, a permit will need to be issued if it is done before Reith Riley gets in there.  A permit will be issued but if it is in the area where they will be working the MOU will need to be addressed.  This is part of the reconstruction around the ballfield that is needing a permit so as long as it doesn’t interfere with Reith Riley’s work a permit will be issued without a problem. 
NIPSCO comments:
Finishing up some work down at Main and Chippewa had a few issues but should be finished up this week.  The roundabout location has no issues with that. 
Bartlett was started this week. Doing some potholing to locate all the underground facilities and will be doing a directional boring line on the west side of Michigan on Monday. Doing some tie-ins and more directional boring on Madison Street and some more tie-ins. Should be done by end of the month Schedule is on track.
Gas line that is being run East/West.  Planned on locations between Madison and Jefferson and ran into conflicts at every intersection.  So we need to replace with a new line on Main Street and some lines will be a bonded.  New ties will have be on Washington to the small alley type street east of main.  Ties going all over the place downtown.  Pre-Con next week with InfoSource. It is up to them on the schedule and they should be mobilizing at the end of the month.  Most work is on Main Street between Madison and Jefferson.  Need to work with Reith Riley regarding schedule to determine when start and finish will take place.  A lot of crews working in several areas so hopefully Nipsco can work with Reith Riley’s traffic control and get all our work done during that time frame.  The lines crossing Main Street will be directional bored under everything. The work on the main street area is expected to take 4 weeks.
Main and Western will be done during our next go around by another NIPSCO crew and should be down within the next 3 weeks. 
 Earliest we can start will most likely be the last week of March and will know better after we meet with our contractor.  Reith Riley would like a set of NIPSCO’s plans so they can coordinate them with theirs.



Page3
AT&T comments:
Couple of manholes down at Bartlett need to be replaced, because of the elevation being too high. Planning on removing existing and replacing the new ones right on top of them.  2 weeks on each manhole starting around first of April.  On schedule for the April 30th deadline of work.
Comcast comments:
No one from Comcast showed up for meeting!
(Ben Holden) from Lawson Fisher had talked to Comcast and they intend to directional bore new lines at Chippewa and Michigan, Ben was unaware of Comcast’s schedule.
South Bend Water Department comments:
Woodruff is going to do the 20 inch water main. They will do the Marion Street roundabout first and the Bartlett street intersection next. They spoke about the rusty water that would get to the downtown business on several different occasions and they will communicate when that takes place.  Every time a shut off is performed to do a relocate, rusty water happens and not much you can do about it.  Town has old pipes and if anything goes bad it goes bad and if it needs shut down it will take hours to get it shut down.  Locates are a bit of a problem now because of the ground being wet but will get it down as soon as we can. Reith Riley will be adjusting water and sewer castings. AEP castings will be done by AEP and it will take 2 to 3 days.
Sewer Department comments:
Locating the sewer castings but that is about all they will be doing. 
Signals and Lights comments:
INDOT is not on 811, you have to contact INDOT directly.  Need to know when signals and Lights take over on Michigan from Sample to LaSalle and once that is clarified Signals and lights will do locates in that area.  INDOT is responsible for everything on Main St. to LaSalle.  
Corbitt is still waiting on getting the signed agreement from INDOT.
MCI/Version to comments:
Has a run on Main Street that goes over head at the rail road tracks that should not be a problem. They have a manhole on Washington on the south west quadrant that needs moved to the west. South Street at north west quad should be 2 feet below structure but needs checked. Not shown on all plan sheets and they do own locates. Do work in conjunction with Reith Riley.  MetroNet cable in the south west corner of Washington and Main going into TCU is in the city duct. Permits on main a joint permit through City and INDOT.



Page 4
Level 3 comments:
Nothing on Michigan and off the right a way quite a bit from Main to Bronson so shouldn’t have any issues.  Will have someone on-call 24/7 if anything comes up.

Infinity Fiber comments:
Working on the west side of Main south of Ewing.  Currently deeper than existing manholes
Sprint comments:
No one from Sprint showed up to meeting
Century Link comments:
No one from Century Link showed up to meeting
MNet comments:
Manhole composite covers at St. Joe and Michigan to pull.  Some things may not be reinstalled that are being pulled but will communicate during those decisions on removing composite covers and replacing them with a standard cover.  Flow censor in manhole not attached to casting Lid.
Metronet comments:
Bartlett 2 handles to be removed.   Pay item for coaction work performed by MetroNet.
Closing
Toney to be onsite all the time for Reith Riley.
Notice to proceed not yet. Bonds are in. Reith Riley needs Contract signed and returned.



Meeting Min done by Myron Cohagan