Tuesday, March 29, 2016

3-29-16

Met with the City of South Bend and Transpo and reviewed Bus routes and the rerouting of the buses during the construction of the down town area. Also discussed the moving of pickup areas and placing temporary signage for the stops.
     Then went and looked at locations for the web cams, with Toy, Josh, Larry Lies and Scott Kirkpatrick. Placing the cams at Bartlett st., Marion Street, Century Center and the parking garage on Main Street.
     Then i met with Bob Strasbourg at the intersection of Marion and Michigan. We reviewed the overhead power lines that will need to be moved. The power pole on the north side of Marion just east of Michigan will, need to be removed by May 21 due to a pipe that will be running right next to it. This in turn will cause 4 street light on the east side of Michigan north of Marion to go down.
     I then talked to Tony Macias about Windstream on the east side of Michigan at Bartlett Street.
He is going to look into it and see if Windstream has a line at that intersection.

Sunday, March 27, 2016

3-25-16

                                                       Progress Meeting Min 3-25-16

Introductions
Schedule
Up Coming Schedule- Reith Riley will start working on Riverside on April 4th. They will start the street scape area downtown around April 21st.
Utility Issues
                Nipsco will be at Colfax and Main for 2 to 3 weeks. They will be working from Lassalle to Colfax should be done by mid-April, Lassalle North should be done by May 7th. InfraSourse is supposed to have a schedule to Nipsco by the end of the day.
                AEP will remove the poles on Bartlett next week from Riverside to Saint Joe Street. Then work on the temporary feed at the ally between Saint Joe and Michigan.
                Comcast had no hard date on the work at Bartlett or the work at Chippewa.
                AT&T i called Denis Bunch after the meeting and he plans on having the line at Bartlett moved ASAP
                US Signal and Windstream at Chippewa was discussed and contact information for Windstream was not known by anyone.
The city will be working on Main Street from Madison to Marion Street next week trying to locate electric duct banks. They city requested Reith Riley to lay out structures in the area to help make sure the Duct banks and sewer lines are not in conflict.
                Additional R/w and Encroachments Marmain is complete, Palmer funeral hope to be signed and done in 30 days, Chase bank by the End of May, Cavalry Temple still negotiating , 5th /3rd Bank still under discussion.
                Submittals Reith Riley requested that when submittals are signed by the designer and more than one designer is involved they do not receive the approval until all three sign off. Roger called JPR was called due to the structures not being completed yet. The Temporary Panel Signs were also discussed that a plan change would have to be made. Reith Riley asked about Rim elevations not being on all the plans. They also requested the CAD files for all the plans so it can be used for layout.
Web Cameras Reith Riley is working on getting the camers and getting them placed. The cost of providing the cameras is on Reith Riley, if the City decides to keep the cameras when the work is done then they will buy them.
                Videoing the Street will be done by a hired company. If the Video work is not done before Reith Riley Starts doing any construction work then Reith Riley will video the area they are working in themselves.
                Construction Sinage: temporary RCA signs will be placed next week. Message board signs will be placed next week on Riverside and Bartlett informing of the closure.
City Concerns: Possible paving by Xavier School prior to the start of the school in August. Ground breaking will be coordinated with the Mayor’s office. The location of the field office was discussed and the use of a building instead of a trail. This will have to be run by Eric.

The next meeting will be held on Tuesday April the 5th.

Thursday, March 24, 2016

3-23-16

Reviewed plans and got the mmp files(schedule) to excel and gave them to Rich to incorperate into smart sheets

3-24-16

Met with Bob Strosburg from AEP, Jay Costello from ComCast and Toney Kaser from Reith Riley at Riverside and Bartlett.  Bob is going to remove the light poles on Bartlett from Riverside to West to the first street, next week. He will then place a temporary pole for the utilities running down the ally just East of Michigan road on the edge of the RW in the Park.Once the storm sewer line being placed by Reith Riley is run past the temporary service a permanent service will be placed under ground. Comcast also has a line running in the same area that is attached to the AEP Pole that needs removed. Comcast is intending to trench in a new line and bore a line deep enough to avoid the new sewer line.  A time line was not given on Comcast work.
       We then went to the South end of the project and met at Bartlett and Michigan St.(Jay, Toney & I). Jay explained how he was going to move the line along Michigan, Chippewa and Main. He informed me that it would be the first of May before this work can be completed. He then informed me that the lower line on the East side of Michigan running North and South was not his cable.
         Upon further investigation it was determined to be US Signals. I contacted Chris Olszewski of US Signal he confirmed he had a line in that area. He plans on having TurnKey get out there as so as possible. He then informed me that Windstream has a fiber line that is bundled with his lines crossing Bartlett. I informed Roger, Toy and Corbitt  of the city  because i did not know who to contact. I am now waiting on further instruction.

Then we had a meeting with Xavier Schools. They explained their concerns of the two way conversion. The time line of road closures was discussed in association with the school year. They talked about the pick up process of the children at the end of the day and how it will be affected. They requested the parking at the front of the school be redone to coincide with the new direction the traffic will be going. The city will have to look into that matter and get right of entry. Roger also informed Rich and Me to be aware of sight distance issues at intersections and drives with the new parking along Main and Michigan. Attendies Roger Nowrot, Toy Villa, Rich Estes, Chris Dressel, (Mrs Grimms, assistant Principle and Business Manager) Xavier School

Wednesday, March 23, 2016

3-22-16

Posted submittals on smart sheets, after talking with Roger. I will post submittals on smart sheets and he will then forward them on the designer of record. The City, AEP and Reith- Riley met about the new conduit runs in the down town area. Reith Riley informed me of the meeting. I also talked to Reith Riley about getting a field office.

3-18-16

Met with Rich Estes about Smart Sheets at 9:00. Talked with Corbitt about submittals. he said all submittals should go to Roger Nowrot and all plan Changes/addendum's should also go to Roger. Roger will then send them to the appropriate designer, for checking. Corbitt also gave me an organizational chart as to the chain of command.

3-21-16

looked at an office location at 328 N Michigan road. worked on More Submittals for Martell on Division A. Posted submittals on smart sheets.