Met with Bob Strosburg from AEP, Jay Costello from ComCast and Toney Kaser from Reith Riley at Riverside and Bartlett. Bob is going to remove the light poles on Bartlett from Riverside to West to the first street, next week. He will then place a temporary pole for the utilities running down the ally just East of Michigan road on the edge of the RW in the Park.Once the storm sewer line being placed by Reith Riley is run past the temporary service a permanent service will be placed under ground. Comcast also has a line running in the same area that is attached to the AEP Pole that needs removed. Comcast is intending to trench in a new line and bore a line deep enough to avoid the new sewer line. A time line was not given on Comcast work.
We then went to the South end of the project and met at Bartlett and Michigan St.(Jay, Toney & I). Jay explained how he was going to move the line along Michigan, Chippewa and Main. He informed me that it would be the first of May before this work can be completed. He then informed me that the lower line on the East side of Michigan running North and South was not his cable.
Upon further investigation it was determined to be US Signals. I contacted Chris Olszewski of US Signal he confirmed he had a line in that area. He plans on having TurnKey get out there as so as possible. He then informed me that Windstream has a fiber line that is bundled with his lines crossing Bartlett. I informed Roger, Toy and Corbitt of the city because i did not know who to contact. I am now waiting on further instruction.
Then we had a meeting with Xavier Schools. They explained their concerns of the two way conversion. The time line of road closures was discussed in association with the school year. They talked about the pick up process of the children at the end of the day and how it will be affected. They requested the parking at the front of the school be redone to coincide with the new direction the traffic will be going. The city will have to look into that matter and get right of entry. Roger also informed Rich and Me to be aware of sight distance issues at intersections and drives with the new parking along Main and Michigan. Attendies Roger Nowrot, Toy Villa, Rich Estes, Chris Dressel, (Mrs Grimms, assistant Principle and Business Manager) Xavier School
Showing posts with label utility. Show all posts
Showing posts with label utility. Show all posts
Thursday, March 24, 2016
Monday, March 21, 2016
3-17-16
At 1:00 pm had a utility meeting with Nipsco, Reith Riley, the City of South Bend and Infra Source.
Discussed was Nipscos plan to upgrade the current lines they have in the downtown area. They want to up grade on Main Street from Madison to Jefferson.with work on Madison, Colfax, Washington, and Jefferson. and a small hook up on Michigan between Washington and Colfax and work on Lafayette North of Washington. Infra Source explained it would take around 10 weks to do all the work. The area will be torn up until the end due to the termination process. Reith Riley has the option to let NIPSCO work in the area,while they are working in the same area. Further discussions will take place to see if the timing can be worked out.
Reps for the City Toy Villa and Roger Nowrot
Reith Riley -Tony Kasar
Lochmeuller- Myron Cohagan
Infra Source- Josh Sargent
Nipsco- Phil Griffen
At 3:00 Pm met with AEP
We discussed the service points to the Vaults. the runs will stop just short of the vault and AEP will finish putting the hole in the Vault and the connection. We reviewed Peberton Davis will do the Division B lighting and Martel will do division A. Tony from AEP will cordinat relocates on the South end from Chippewa to Western. Fran will handle Western To LaSalle and Bob will handle LaSalle North. Robert Henry will be handling the light removal. Bob pointed out some poles on Riverside will need to be moved and lighting in that area will be affected. The poles at riverside should be removed by April 4th. Bob also pointed out the electric issues with the sign at Marion and the electric involved with the removal of the Mar main building. During the placement of new lighting AEP will work with the contractors and the city to try and limit the number of poles taken out of service at a time.
Lochmueller -Myron Cohagan
City - Toy Villa
Reith Riley- Tony Kasar
AEP -Antonio Macias, Fran Glen, Bob Strasburg
Discussed was Nipscos plan to upgrade the current lines they have in the downtown area. They want to up grade on Main Street from Madison to Jefferson.with work on Madison, Colfax, Washington, and Jefferson. and a small hook up on Michigan between Washington and Colfax and work on Lafayette North of Washington. Infra Source explained it would take around 10 weks to do all the work. The area will be torn up until the end due to the termination process. Reith Riley has the option to let NIPSCO work in the area,while they are working in the same area. Further discussions will take place to see if the timing can be worked out.
Reps for the City Toy Villa and Roger Nowrot
Reith Riley -Tony Kasar
Lochmeuller- Myron Cohagan
Infra Source- Josh Sargent
Nipsco- Phil Griffen
At 3:00 Pm met with AEP
We discussed the service points to the Vaults. the runs will stop just short of the vault and AEP will finish putting the hole in the Vault and the connection. We reviewed Peberton Davis will do the Division B lighting and Martel will do division A. Tony from AEP will cordinat relocates on the South end from Chippewa to Western. Fran will handle Western To LaSalle and Bob will handle LaSalle North. Robert Henry will be handling the light removal. Bob pointed out some poles on Riverside will need to be moved and lighting in that area will be affected. The poles at riverside should be removed by April 4th. Bob also pointed out the electric issues with the sign at Marion and the electric involved with the removal of the Mar main building. During the placement of new lighting AEP will work with the contractors and the city to try and limit the number of poles taken out of service at a time.
Lochmueller -Myron Cohagan
City - Toy Villa
Reith Riley- Tony Kasar
AEP -Antonio Macias, Fran Glen, Bob Strasburg
Sunday, March 20, 2016
3-16-16
Worked on Meeting min. submittals and met with Robert Henry and Reith Riley.
At the meeting it was Tony Kasar from Reith Riley and Robert Henry's project Manager. The meeting was to discuss the AEP conduit being placed in the down town area of Main Street that will affect the work Reith Riley has to do. Robert Henry will also be doing some work for Comcast in the same trench that they are doing for AEP. Robert Henery estimates it will take them 3 months to do all the work they have to do. They have work on the east and on the west side of main street, which will cause issues with having Reith Riley in the same area at the same time. They also informed Reith Riley of an AT@T line at the intersection of Western and Main that is in the pavement.