Wednesday, June 7, 2017

6-7-17

Controlling Operation Bartlett: Punch List
Controlling Operation Marion: Punch List
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny    PM Mostly Sunny 
Hi 74 Lo 58

The walk through was held for Main Street and MLK from LaSalle to Western.

Pemberton Davis had a 5 man crew working at the intersection of Wanye and Main.

Pemberton Davis had a 2 man crew painting at Monroe and Main.

Slussers had a 4 man crew working on Sodding and placing edging in various areas.



Walk Through for Downtown Two-way Conversion
Main St.
·         Parking spots striped on the south side of LaSalle, just east of Main St.
·         Temporary straight arrow removed on southbound Main St. at LaSalle.
·         Concrete needs poured at SE corner of LaSalle and Main St. strain pole base.
·         River rock needs to be added next to sidewalk on the east side of Main St. behind the Morris.
·         The no parking sign on Washington near Lafayette needs changed/ moved to be at the end of the stall.
·         All banner arms need to be moved to be away from traffic of light poles and removed from all poles in intersection bump-outs.
·         Trees need to be secured better.
·         Fill in all paver joints with more sand wherever needed.
·         Sweep sidewalk, cycle track and road.
·         Finish any striping left.
·         Grout under mast arms.
·         Northwest corner of Main and Western is missing a trash can.
·         Grout under Mast Arms were needed.
·         Check all Walk/Waits some not working
·         Clean Push ped North east corner
·         Need stone behind sidewalk at Morris drive(landscape rocks/2’s)
·         No right on red signs
MLK Blvd.
·         Take down informational two-way conversion signs.
·         Duct taped plant needs replaced on east side of MLK north of Wayne.
·         Wire sticking up in sod between Century Center parking lot and sidewalk, south of Jefferson.
·         Dead sod in front of the Century Center.
·         Brick paver band on southeast corner of Washington and MLK needs adjusted.
·         Cut off excess concrete on cabinet base and pour concrete around cabinets on southeast corner of Washington and MLK.
·         Pour concrete around Cabinet and Tesco at South East corner of Jefferson and MLK
·         Place sod behind cabinets Jefferson and MLK South East quad
·         South west Corner Jefferson MLK Cut and Cap line lower
·         Saw cut groove in sidewalk between Washington and Jefferson on MLK
·         Move bike sign south of Washington farther south to next concrete pad
·         Water Fountain
·         Remove INDOT mile marker just north of washington
·         Fill in Concrete around hand hole South East corner Jefferson and MLK
·         Cut off pipe at northeast corner of Washington and MLK.
·         Order spare snow markers.
·         Paint top of curb at Colfax and MLK south east and North East.
·         Sweep at century center parking lot
·         Remove no parking signs on School building light poles
·         Wisco pipe North east corner Washington and MLK
·         Double tree irrigation
·         Covers for back flow
·         Stain man hole bike path brick areas
·         Straighten Light heads that have spun
·         Calk cabinet bottoms
·         Sod LaSalle east of MLK before bridge small area
·         Yellow thermos over patch between Colfax and LaSalle
·         West bound LaSalle white stripping between Williams and Lafayette
·         Yellow curb top at LaSalle and Main South East corner
·         Pull all Dead Trees and replace this fall
·         Concrete sidewalk South east corner of Sample and main
·         Concrete Service walk on Michigan South of Madison west side north parking area
·         Concrete sidewalk slab remove west side of Michigan north of LaSalle





6-6-17

Controlling Operation Bartlett: Punch List
Controlling Operation Marion: Punch List
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny    PM Mostly Sunny 
Hi 74 Lo 52

Reith riley had no one on site today.

Pemberton Davis had a 5 man crew remove the receps by the hospital. they worked on Western and main hooking up the loops.

Pemberton Davis had a 2 man  crew painting the poles at Monroe and MLK.

No other work took p[lace today  

Monday, June 5, 2017

6-5-17

Controlling Operation Bartlett: Punch List
Controlling Operation Marion: Punch List
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny    PM Mostly Sunny 
Hi 82 Lo 58

Pemberton Davis had a 5 man crew working on replacing the lights that had been hit on main street and Martin Luther King. They also worked on pushing conduit under Laffayette north of LaSalle

No other work took place today.

Friday, June 2, 2017

6-2-17

Controlling Operation Bartlett: Punch List
Controlling Operation Marion: Punch List
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny    PM Mostly Sunny 
Hi 82 Lo 48

Reith Riley had not on site today.

Pemberton Davis had a 2 man crew painting Mast Arms at South and Michigan.

Pemberton Davis had a 4 man crew working on Main and LaSalle and MLK and Western.

Wisco had a 4 man crew working on fixing irrigation.


Meeting Agenda
Meeting With:
Reith Riley & City of South Bend


Meeting Date:
6-2-17


Regarding:
Two Way Conversion Weekly Progress Meeting

Construction and Utilities



ITEMS TO BE DISCUSSED

9:00 AM Introductions/Sign in

The Weeks up Coming Events/Schedule
1. Rieth Riley: Wisco will be on site finishing repair work on irrigation they should be done in 2 weeks. Airmarking has miscellaneous epoxy and thermos work to do once the pave drain is resolved. Slussers will be in next week and try to finish punch list items.

                                2. Pemberton Davis: will be working at Lafayette and LaSalle Monday and Tuesday. They will finish any wiring neede done. They will work on the Cabinets that need rewired.

Utility Relocation Issues:
AEP: 
1.       Michigan and Indian
2.       Poles on Marion east of Michigan: AEP is working on this with AT&T
Robert Henry:
           
Metronet: 
                 
                Transpo: No Questions
               
                311
               
                DTSB : Asked about the left turn at Monroe and Michigan heading east.

Utilities Q/A

INDOT: Questions:   

Stakeholder Questions: Memorial Hospital

Larry will wait a couple more weeks before placing locks on backflow preventers.
I will walk the north section next week to review what needs fixed from the punch list.

Action Items  

1.       Pave drain: I will call and talk to Steve Benzick from INDOT to discuss the repair limitations as to what is acceptable and what is not. Rieth Riley will have a crew available possibly the 19th or the 26th to get the work done. Once the fix is agreed upon.

2.       Chase Tower: has moved the barrio and now pemberton Davis can get in and do the work on that corner to get the signal operational.

3.       Irrigation, Double Tree, Burger King: Wisco should have this work done in2 weeks.

4.       Tree grate and Brick Storage 7 tree grates will need to be stored and 65 pallets of brick once the City figures out where they want them placed.

5.       Traffic accidents: that have no insurance will be paid through the contract, the city insurance has too big of a deductible.

6.       Parking stalls Wayne Street Michigan to Main utility work is completed in this area and can now be striped

7. Weekly Progress meetings: keep having them until the pave drain is resolved.
               
Reith Riley Construction Concerns/Questions

City Concerns/Questions

The City would like to know if white bike emblems can be added to the green cross walk areas.

June 21st Main Street will be closed from 10:00am to 12:00 pm to dedicate the MLK Statue at the Leighton Plaza

The tentative date for the ribbon cutting will be June 16 at the Century Center.

I need to look into the stop sign installed at the corner of MLK and Wayne street North east.



Thursday, June 1, 2017

6-1-17

Controlling Operation Bartlett: Punch List
Controlling Operation Marion: Punch List
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny    PM Mostly Sunny 
Hi 74 Lo 48

Reith Riley had no one on site today.

Pemberton Davis had a 4 man crew working at LaSalle and Main redoing the push peds. 

Pemberton Davis had a 2 man crew working on painting at Bronson and Main Street.

Pemberton Davis had a 3 man crew working at Wayne and Michigan placing thermo detection.

Wisco had a 4 man crew working on the irrigation repairs on Main Street and MLK.

No other contractors were on site today. 

Wednesday, May 31, 2017

5-31-17

Controlling Operation Bartlett: Punch List
Controlling Operation Marion: Punch List
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny    PM Mostly Sunny 
Hi 68 Lo 48

Reith Riley had no one on site today.

Metro Net tore up to run fiber in front of the Century Center.

Pemberton Davis had a 4 man crew working on the thermal detection at Colfax and MLK. They then went to Main and LaSalle and worked on the push peds. They also worked on the thermo detection at MLK and LaSalle.

Pemberton Davis had a 2 man crew painting the mast arms at the intersection of Michigan and Bronson.

Pemberto Davis had a 4 man crew cutting loops at the intersection of Sample and Main and Sample and Michigan.

Air Marking had a 3 man crew working on Parking stalls and any other miscellaneous work.

Slussers was in and placed sod on Michigan from LaSalle North to Navarre. They then placed it at Bronson and Main Street.

Wissco had a 4 man crew working on irrigation at various locations.



Tuesday, May 30, 2017

5-30-17

Controlling Operation Bartlett: Punch List
Controlling Operation Marion: Punch List
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny    PM Mostly Sunny 
Hi 76 Lo 48

Reith Riley had no one on site today.

AirMarking had no one on site today.

Pemberton Davis  had a 2 man crew pulling wire at Main and Sample.

Pemberton Davis had a 5 man crew putting in Detector housings at Sample and Michigan. they then went to Lafayette and LaSalle and placed the 5 section heads.

Pemberton Davis had a 4 man loop crew working at Main and Western then they went to Main and Sample.

Wisco had a 4 man crew working on repairs on main and MLK

Slussers not on site today.