Friday, February 10, 2017

2-10-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Partly Cloudy PM Cloudy   
Hi 38 Lo 18

Pemberton Davis worked on pouring foundations for street lights on the east and west side of Saint Joe between Colfax and LaSalle. They also worked on the walk waits for Bronson and Main.

No other work took place today.

Phil @ Pemberton; "MLK and La Salle ; lighting foundations on south side of intersection. Had to hand dig due to utilities in area."




Meeting MINUTES
Meeting With:
Reith Riley & City of South Bend


Meeting Date:
2-10-17


Regarding:
Two Way Conversion Weekly Progress Meeting

Construction and Utilities



ITEMS TO BE DISCUSSED

9:00 AM Introductions/Sign in

The Weeks up Coming Events/Schedule
1. Reith Riley- will continue to work on the snowplow markers as weather permits
                                2. Pemberton Davis- Pemberton Davis will work on streetlights north of LaSalle on Main and Michigan. They will also work on signs no parking/chevrons on the roundabouts/Marmain loading zone. 
Utility Relocation Issues:
AEP: 
1.       Power at Wayne and Main- will get next week
2.       Power at Colfax and Saint Joe Both meters-will get next week
3.       Jefferson and saint Joe along with Washington and Saint Joe- next week
Robert Henry:
1.       Vault at Main and LaSalle- need a work order from AEP and they will get it done as quick as possible          
Metronet: 
1.       WIFI on Saint Joe and Main Pemberton Davis Gave a list to MetroNet. Metronet will work on the intersections that are done, but the Wi-Fi will stay down until all locations are completed.
2.       Metronet will be running a feed to the LaSalle grill on main Street and a side walk panel is cracked they wanted to bring to the attention before they       
NPSCO:
                                1 Work left on Michigan Street- will get with Robert Henry and the City to keep thing moving.
Utilities Q/A

INDOT: Questions:
The permit for this project expires in March and needs to be extended; Roger will take care of that.   

Stakeholder Questions: Larry asked about the crosswalk lights at Bartlett, tanner expects the parts in next week and hoping to have it fully functional the following week. Don’t forget the light pole at Bartlett and Main. When will all the lights from Marion North be done, end of February.


Thursday, February 9, 2017

2-9-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy light snow PM Cloudy light Snow  
Hi 22 Lo 18

Pemberton Davis worked on street lighting on the east and west side of Saint Joe. They assembled and set the lights from Jefferson to Colfax on Saint Joe and the 2 just north of Jefferson on the east side of Saint Joe. 

No Other work took place today. 

Phil @ Pemberton; "MLK Blvd lighting; installed lights on foundations north of Jefferson to Colfax. 
MLK and Washington; removed pedestrian signals and poles around the intersection." 

Wednesday, February 8, 2017

2-8-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy  PM Cloudy light Snow  
Hi 34 Lo 28

Pemberton Davis worked on pulling wire and setting lights on Saint Joe Street from Colfax to Jefferson on the east and west side of the street.

No other work took place today.

Phil @ Pemberton; "MLK Blvd lighting; installed conduit in several locations north of Jefferson to Colfax. 
MLK and LaSalle ; removed pedestrian foundation on SW corner. 
MLK and Colfax; removed pedestrian pole and foundation."

Tuesday, February 7, 2017

2-7-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Mostly Rain  PM Cloudy Rain  
Hi 56 Lo 48

No work today due to the heavy Rain.


Monday, February 6, 2017

2-6-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Mostly Sunny  PM Partly Cloudy  
Hi 45 Lo 28

Pemberton Davis worked on the street lighting on Saint Joe Street from LaSalle to Colfax on the East side of the road they finished pouring the foundations. They also worked on getting the actuation working on South Street and Michigan that started working around 10:45 AM.

Reith Riley worked on setting the snow plow markers on Saint Joe Street.

No other work took place today.

Phil @ Pemberton; "Michigan and South St. ; TCC programmed cameras all working fine. 
Main and South St. ; set more pedestrian signals no SE corner. Also removed existing. 
MLK Blvd lighting; installing light base between Jefferson and Colfax."


Friday, February 3, 2017

2-3-17


Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM cloudy windy cold  PM Cloudy  
Hi 26 Lo 16

Pemberton Davis continued to work at the intersection of Michigan and South Street. They hung the heads on the South Bound Mast arms and finished wiring the intersection. The City then inspected the work and the signal was activated around 3:30. 

Phil @ Pemberton; "Michigan and South St. ; set SB signal heads, had to cover heads. Spliced poles and cabinet. Removed all bags and turned signals on at 3:15 pm. 
Main and South St. ; removed existing pedestrian signals and installed new pedestrian signals and push buttons."

2-2-17


Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Partly Cloudy  PM Mostly Sunny
Hi 27 Lo 16

Pemberton Davis had a 7 man crew on site. They set the Tesco Cabinet and they moved the Controller Cabinet at the intersection of South an Michigan. They also strung new wire to up the strain poles. 

AEP showed up and ran power to the new Tesco that was completed around 1:00 PM. 

No other work took place today.

Phil @ Pemberton; "Michigan and South St. ; set pedestrian poles around intersection along with pedestrian signals and push buttons. Installed signal cable around the intersection and in SB mast arm. Set new signal cabinet and Tesco. Installed 3" and 1" conduit at Tesco cabinet."