Tuesday, November 8, 2016

11-8-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Removals
Fraction of Day workable 10/10
AM Cloudy Light Rain  PM Cloudy Light Rain 
Hi 59 Lo 42

Reith Riley Had a concrete crew working on pouring cycle track from Madison to LaSalle on the east side of Michigan. A second crew worked on pouring curb at the North east corner of Main and Western. A third crew picked up miscellanies items on Main Street. A curb crew worked on Saint Joe street from Jefferson to Wayne.

Reith Riley had a prep crew working on placing stone in the curb areas on Main Street on the east side from Jefferson to Colfax. A second prep crew worked on the century center drive to the loading dock and the side walk on Michigan.

Indiana Earth had a crew doing removals at the North west corner of Michigan and LaSalle. They had a second crew working on grading for curb from Washington to Wayne. 

Pemberton Davis had a crew working on setting up street lights on the east side of Main street. They had a second crew working on pouring strain pole foundations on Colfax and saint Joe and a third crew placing conduit on the west side of saint Joe from Colfax to Washington.

Woodruff worked on placing structures on the east side of Saint Joe between Washington and Colfax.

Slussers worked on planting trees on Bartlett and Riverside they then moved to the Bartlett round about.

Monday, November 7, 2016

11-7-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Removals
Fraction of Day workable 10/10
AM Sunny  PM Sunny 
Hi 69 Lo 42

Reith Riley had a concrete crew working on the South West corner of Main and Western. A Second crew was working on the ramps in front of the library. A third crew worked on the cycle track on the east side of Michigan from Madison to LaSalle.

Reith Riley had an Asphalt crew working on paving the intersection of Main and Monroe, Main and Washington, the alley between Jefferson and Wayne and the Saigon parking lot.

Reith Riley had a prep crew working on the stone for bricks on Main Street. a Second crew worked on grading for side walk north of LaSalle on Michigan.

Indiana Earth continued to do removals on saint Joe between Washington and Colfax. A second crew worked on Saint Joe removals between Wayne and Jefferson. a third crew worked on grading between LaSalle and Colfax behind the curb on the east side.

Slussers was on site and planted trees on Bartlett Street from Riverside to Michigan and North of Bartlett on Michigan. 

Wisco was on site doing repairs.

Pemberton Davis worked on the foundations at the intersect on of LaSalle and Michigan and Colfax and Saint Joe.

Air Marking not on site

Sunday, November 6, 2016

11-5-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Removals
Fraction of Day workable 10/10
AM Sunny  PM Sunny 


Hi 72 Lo 39

Reith Riley had no one on site today.

Pemberton Davis only had Phil on site today and the boring copy.

Air marking was on site working on the side streets.

Friday, November 4, 2016

11-4-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Removals
Fraction of Day workable 10/10
AM Sunny  PM Sunny 


Hi 69 Lo 44

Reith Riley had a concrete crew finish the cycle track on the east side of Main Street between Wayne and western . A Second crew worked on the South East corner of Wayne and Main. A third crew worked on the the parking stall on the east side of Michigan between LaSalle and Madison.

Reith Riley had two prep crews working on the east side of Main Street placing stone for the bricks that go between the sidewalk and curb. 

Reith Riley had a milling crew come in and start milling around casting and valve boxes on the east side of Saint Joe between LaSalle and Western

Woodruff had a crew placing structures on the east side of Saint Joe between Jefferson and Washington.

Indiana Earth had 2 crews working on removals on the east side of Saint Joe one crew worked between Colfax and Washington and the second between Jefferson and Wayne.

Pemberton Davis worked on setting the foundations for the strain poles at the corner of LaSalle and Saint Joe Street. 

Slussers was in and planting trees on Bartlett street from Main to Michigan.

Wisco had guys working on the south east corner of Marion and Michigan. 



Meeting Minutes
Meeting With:
Reith Riley & City of South Bend


Meeting Date:
11-4-16


Regarding:
Two Way Conversion Weekly Progress Meeting

Construction and Utilities



ITEMS TO BE DISCUSSED

9:00 AM Introductions/Sign in

The Weeks up Coming Events/Schedule
1.       Traffic Closure Updates
A.       Colfax/Jefferson/Washington/Wayne: Monday Main and Washington resurface Main and Monroe minor delays due to resurface/ LaSalle and Lafayette Late week
                                        B.       Saint Joe: will remain on the west side should not be to many delays

Utility Relocation Issues:
AEP:  

Robert Henry:
1.       Washington and Michigan: should be open Monday. Continue to work south on Michigan. Concrete will be fully patched come spring/partial patch for winter

NIPSCO/InfraSource:   Needs LaSalle and Lafayette paved later in week. Leighton plaza brickwork this week, also need patch work at Colfax and Washington, also need work at Wayne and Michigan going to wait until Robert henry done.
            
Comcast: 

                AT&T:     

Water Dept:     Water Taps worked out with woodruff for irrigation

Transpo:    
               
Metronet:     Meet with Pemberton Davis Monday to go over Main and Saint Joe WIFI that needs removed and that can go back up.
                 

Utilities Q/A

INDOT: Questions:    None

Stakeholder Questions: Handrail to steps by hospital should happen in the next week. Water preventers need to have covers put on them. Barricades in the parking lot will be removed today. Larry would like a set of landscape plans for Bartlett. Reith Riley will work on getting A-1 to stripe the parking lots.

Main Street Row: did not show but was determined they need to wait until the brick is placed next week.

10:00 am 10:10 Break Utility and Stakeholders can leave


Action Items
               
1             Upcoming work for the week: continue to work on Main street placing brick between the curb and cycle track. Work on sidewalk as available and work on street lighting. Work on stripping the side streets. On Saint Joe finish drainage structures, place the curb on the east side and resurface the east side. Continue landscaping to the north.

2             Western And Main South West Corner: Roger will get with Structure point.

3             Scheduled \opening
     A. Traffic Signals Poles come in on the seventh Colfax and LaSalle can be done by the 15th.
     B. Markings: continue to work this week.

4             Saigon Parking lot fence: Toy should have the fence ordered next week.

5             Main Street Bridge lighting: Tanner will get pricing next week

6             Getting ready for Winter/expectations: work as long as they can until they have to cover the concrete.

                                               
Reith Riley Construction Concerns/Questions:

The extra pave drain mats will be sent to organic resources.
Guardrail at the bridge a decision is still pending.

City Concerns/Questions: It was decided to open Saint Joe to two way traffic on Nov 23rd  due to the strain poles coming in so late and it would allow for the side streets of Jefferson and Washington to be completed
                               
 Next weekly progress meeting 11-18-16




Thursday, November 3, 2016

11-3-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Removals
Fraction of Day workable 10/10
AM Cloudy  PM partly Cloudy 
Hi 64 Lo 58

Reith Riley had a concrete crew work on the South East corner of Wayne and Main. They had a second crew working on the cycle track in font of the library. A curb crew worked on the east side of Saint Joe from LaSalle to Colfax. A fourth crew worked on the South west corner of Saint Joe and the Morris drive doing sidewalk.

Reith Riley had a prep crew working on placing the 8's on the west side of Main from Wayne to Jefferson. A second prep crew worked on saint Joe street. 

Indiana earth continued to do removals on the east side of Saint Joe from Washington to Colfax. They also worked on grading on the east side of Main street between the curb and sidewalk,

Pemberton davis worked on the east corner of Main and Wayne. They also worked on setting pole foundations on the east side of Saint Joe from LaSalle to Wayne.

Slussers was in and planted trees at Bartlett west of Michigan. 

Wisco continued to work in front of McDonald's.

Wednesday, November 2, 2016

11-2-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Removals
Fraction of Day workable 10/10
AM Partly Sunny  PM Cloudy 
Hi 71 Lo 58

Reith Riley has a concrete crew pouring the cycle track from Wayne to Western on the East side of Main Street. A Second crew is pouring the South East corner of Main and Wayne. A third crew worked on pouring side walk on the west side of saint Joe between Morris drive and LaSalle. When they were done with that they worked on finishing the center islands on Saint Joe between Wayne and LaSalle.

Air Marking is working on striping from Sample ton Monroe on Michigan. They also had a detail crew working on Michigan between Sample and Monroe on Michigan. They had a crew doing removals on the side streets between Lafayette and Saint Joe.

Reith Riley had a prep crew placing 8's and filter cloth for the brick pavers between LaSallle and Wayne on the west side of Main. A second prep crew worked on resetting the tree grates on Main Street.

Pemberton Davis worked on digging and pouring foundations for light poles and strain poles on Saint Joe street from LaSalle to Wayne on the west side of the road. They also worked on placing conduit from foundation to foundation. They had a second crew working on the pucks at the intersection of Michigan and North Shore. They had a crew pushing conduit at Angela and Michigan for the new detector housings.

Woodruff changed some grates around and moved things around and then went home because nothing was ready for them to work on.

Indiana Earth worked on grading out between the curb and side walk on the east side of main street from LaSalle to Western. They also had a second crew on the east side of Saint Joe doing removals from Jefferson to Colfax.

Wisco was on site working on the east side of Michigan between Marion and Madison.

Reith Riley had a Milling crew come in late and mill the patch on Main at Monroe and the water hole on Wayne east of Main and the parking lot/alley between Jefferson and Wayne.

Tuesday, November 1, 2016

11-1-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Removals
Fraction of Day workable 10/10
AM Sunny  PM Sunny 
Hi 76 Lo 58

Reith Riley had a crew on site paving the approaches to the west side of Main Street from Bronson to Jefferson. They then went and worked on the patches for Robert Henry.

Reith Riley had a prep crew moving the tree grate boxes on the east and west side of Main per Mike Divita. A second crew worked grading out on Saint joe Street on the west side between the Moris and LaSlle street. 

Wisco worked on the east side of Michigan between Madison and Marion.

Reith Riley had a concrete crew working on the west side of Main north of Jeferson doing cycle track a second crew worked on the east side of Main north of Wayne. A third crew worked on the east side of main doing cycle track between Wayne and Washington.

Woodruff worked on structure 164 at the intersection of Washington and Main. This structure is complete.

Pemberton Davis worked on setting light pole foundations on the east side of Main street from Western to Jefferson. They also worked on strain pole foundations on Saint Joe from Wayne to LaSalle.

Air Marking worked on placing the detail work on Michigan and Main from Ewing to Sample. They also laid out and striped from Western to Sample on Michigan. They also worked on the line removal into the downtown area from Lafayette to Saint Joe and LaSalle to western.

Slussers did lay out for trees on Bartlett and Marion.