Thursday, July 14, 2016

7-14-16

Controlling Operation Bartlett: Wall Construction
Controlling Operation Marion: PCCP Pavement
Controlling Operation Lasalle to Ewing: Storm Pipework
Fraction of Day workable 10/10
Hi 84 Lo 66
Weather Am Mostly Sunny PM Mostly Sunny

Rieth-Riley had a concrete crew which poured the southbound lanes of Main St. from approximately Line MAI Sta. 716+26 to Sta. 717+47. In the afternoon they set forms for the next section north. 

Woodruff installed a water valve in the center of Madison St. just west of Michigan. They then moved to Washington and finished the storm structure work at the northwest corner of Main and Washington.

Pemberton Davis set a handhole at the northwest corner of Main and Jefferson. They ran conduit across Jefferson on the west side of Main St. 

Ziolkowski stripped forms from the Bartlett roundabout walls. The rest of the forms will be taken off tomorrow. They also tied and set cages for the concrete foundations of the Marian roundabout walls. JPR provided revised drawings to the wall at the southeast corner misses the existing manhole.

Indiana Earth was not observed on site today.

Patrick Wooden from Structurepoint was on site viewing the Saigon market lot and the new sidewalk and curb on main between LaSalle and Colfax. Game plans were made for both of these issues.





7-13-16

Controlling Operation Bartlett: Wall Construction
Controlling Operation Marion: PCCP Pavement
Controlling Operation Lasalle to Ewing: Storm Pipework
Fraction of Day workable 10/10
Hi 86 Lo 68
Weather Am Mostly Sunny PM Mostly Sunny, Short Period of Rain in Late Afternoon

Rieth-Riley crews did not pour any concrete in Division B. The only Rieth-Riley crew in Division B arrived at Main and Bronson at 2:30 pm and began setting forms on the west side of Main south of the railroad bridge.

Woodruff completed storm structure and pipe work at the intersection of Main and Western.

Pemberton Davis placed two mast arm foundations: one at the northwest corner of Main and Colfax and another on the southwest corner of Main and Western.

Indiana Earth was removing pavement on the west side of Main St. just north of Washington.

Ziolkowski was on site removing bracing from the Bartlett wall formwork and setting up to begin work at the Marian roundabout.




Tuesday, July 12, 2016

7-12-16

Controlling Operation Bartlett: Wall Construction
Controlling Operation Marion: PCCP Pavement
Controlling Operation Lasalle to Ewing: Storm Pipework
Fraction of Day workable 10/10
Hi 89 Lo 71
Weather Am Mostly Sunny PM Sunny

Ziolkowski poured the center monument foundation and all concrete walls in the center of the Bartlett roundabout. They will take down all bracing tomorrow and remove formwork on Thursday (7/14).

Rieth-Riley had a concrete crew poured curb and curb and gutter on the northwest corner of Colfax/Main, the southwest corner of LaSalle/Main, and on the west side of Main between Colfax and LaSalle.

Rieth-Riley's grading crew laid patching asphalt on Michigan St. between LaSalle and Madison.

Woodruff had a crew finishing storm structure work on the west side of the intersection of Western/Main. They will move to Washington and Main tomorrow (7/13).

Indiana Earth was removing pavement on Main between Washington and Colfax. They also removed curb and sidewalk from the southwest corner of Main and Western and curb from the northwest corner of Main and Washington.

Pemberton Davis was working on lights on the southwest corner of the Bartlett roundabout.








7-11-16

Controlling Operation Bartlett: Wall Construction
Controlling Operation Marion: PCCP Pavement
Controlling Operation Lasalle to Ewing: Storm Pipework
Fraction of Day workable 10/10
Hi 89 Lo 63
Weather Am Mostly Cloudy PM Mostly Sunny

Rieth-Riley had a concrete crew pouring sidewalk and integral curb in the Bartlett section. Sidewalk was poured in the southwest corner of the roundabout and extends south to the crosswalk that crosses Michigan south of the roundabout. Curb was placed around the outside of the roundabout. The crew also poured the lower footing for the concrete steps south of Michigan west of the roundabout.

A second Rieth-Riley crew placed a temporary gravel crosswalk on the southwest corner of Main and Jefferson.

Indiana Earth removed sidewalk, curb, and pavement from the southwest corner of Main and Western in the morning. They also removed pavementfrom the southwest corner of Main and Jefferson. Another crew spent the day backfilling on the west side of Main between Lasalle & Colfax for the placement of curb.

Ziolkowski had a crew doing final preparations for the concrete wall pour in the center of the Bartlett roundabout that will take place in the morning (7/12).

In general, it was a very light day in Division B, with very limited work being done in the downtown area. Numerous areas of downtown have been removed and not yet put back.





Saturday, July 9, 2016

7-9-16

Controlling Operation Bartlett: Wall Construction
Controlling Operation Marion: PCCP Pavement
Controlling Operation Lasalle to Ewing: Storm Pipework
Fraction of Day workable 10/10
Hi 72 Lo 57
Weather Am Mostly Cloudy and Humid  PM Mostly Sunny

Rieth-Riley had a concrete crew pouring sidewalk and curb ramps west of Michigan near the Bartlett roundabout. After completing two curb ramps and a section of sidewalk the crew moved to the Marian roundabout and poured the sleeper slab in the southeast quadrant. Crews worked from 7:00 am to 12:00 pm.

Rieth-Riley has an asphalt crew laying binder and the intermediate layer on Marian and Main along Line PR-A from Sta. 17+00 to Sta. 22+45.








Friday, July 8, 2016

7-8-16

Controlling Operation Bartlett: Wall Construction
Controlling Operation Marion: PCCP Pavement
Controlling Operation Lasalle to Ewing: Storm Pipework
Fraction of Day workable 10/10
Hi 86 Lo 67
Weather Am Overcast and Humid  PM Mostly Sunny

Rieth-Riley had a concrete crew pouring sidewalk on the northwest and southwest corners of the Bartlett roundabout and a curb ramp on the north side of Bartlett just west of the roundabout.

Rieth-Riley had a second crew pouring curb for the splitter island west of the Marian roundabout and curb and gutter on Marian St. between Main and Michigan.

Ziolkowski informed Rieth-Riley that they would not be pouring the concrete walls until next week Tuesday (7/12). Their crew continued forming the walls.

Woodruff continued installing storm pipe and structures on the west side of the Main and Jefferson intersection.

Indiana Earth removed the northwest side of the intersection at Main & Western Streets.  They also removed another small section of sidewalk on the west side of Main between Washington and Jefferson near the courthouse.

The plumber was on site at the Madison Oyster Bar rerouting the water line. All utility work in the vault is now complete and the next step will be Ziolkowski installing the masonry wall.

Reith Riley brought a prep crew in late and patched Colfax back in so it would be open to traffic for Monday.

The weekly utilities meeting was held at the field office this morning. Meeting Minutes are attached.





Meeting With:
Reith Riley & City of South Bend


Meeting Date:
7-8-16


Regarding:
Two Way Conversion Weekly Progress Meeting

Construction and Utilities



ITEMS TO BE DISCUSSED

9:00 AM Introductions/Sign in

The Weeks up Coming Events/Schedule
·        Update:  This past week, Rieth-Riley continued pouring sidewalks and began pouring the inside walls of the roundabout at Bartlett Street.  At the Marion roundabout, curb was poured and a base layer of asphalt was laid from Marion west of the roundabout to Madison Street.  Pipe and structure work continued in the downtown area at Jefferson and Wayne on Main Street.  Rieth-Riley finished fine grading on the west side of Main between South and Bronson Streets.  The paving crew has been working on the roundabout at Chippewa all week.
·        Upcoming: Next week, Rieth-Riley will pave the remainder of the Marion roundabout and continue laying asphalt in the area.  Downtown, there are plans to patch Colfax Street on Saturday (7/9) so that the intersection at Main & Colfax can reopen by Monday (7/11).  Once Colfax has reopened, Washington Street will be closed so that removals and pipe work can begin at the intersection of Main & Washington.  Crews will begin laying curb on the west side of Main at Lasalle Street and continue working south from there.  Forms for pavement will be laid on the west side of Main between South and Bronson ahead of paving crews moving in late next week.  Finally, milling is set to begin on Michigan Street between Ewing and Sherwood during the day on Thursday (7/14).  This section of road should then be re-paved on Friday (7/15).

Utility Relocation Issues:
AEP:   Work to adjust the vault on the southwest corner of Bartlett Street began this past Thursday (7/7).  As for the vaults located in the parking lane on the west side of Main between Lasalle and Colfax, David was under the impression that the tops were to be knocked off and the vaults filled.  David relayed that he would check to see if this had been done yet – if not, he’ll make sure it gets done before Rieth-Riley begins laying curb.

Robert Henry:  Work on the duct bank at Michigan and Navarre has been completed and Rieth-Riley plans to fill the resulting trench while they work on Saturday (7/9).  David will verify that his crews are done working on Washington and Main.  He noted that he has been coordinating with the JMS building to determine a good time to lay AEP’s new duct bank in the area.

NIPSCO/InfraSource:  Phil said that his crews are still on track to be completely done retiring lines in the area by Monday (7/11).
            
Comcast: I talked with Jay this morning.  During the conversation, Jay relayed that a Comcast vault may exist underneath the Palmer parking lot near the curb line on Chippewa Street.  Depending on the location of this vault, this may require moving the Palmer approach in one direction or another. 

               AT&T:  Toy has not yet been able to contact AT&T about their work at the JMS building.  During the meeting, Tony also brought to light a concern regarding the ped at the intersection of Main and Marion.  I will call Dennis to confirm, but I believe this line is able to be cut.

Water Dept.:  Ed stated that his crews should be done working at the Chippewa roundabout by next week.  Tony mentioned that after talking with Bob about the old valve boxes along Main Street, he thinks it might be best to simply replace these old valves with new ones.

Transpo: Michael from Transpo didn’t show this week, but removals for the construction of Transpo’s temporary approach did occur this week.

Metronet:  Ben relayed that Martell is awaiting the delivery of a part necessary to repair the busted conduit at the intersection of Main and Jefferson.  He hopes to have this part and repair work done by the end of next week.  Regarding the line hit at Main and Colfax, Ben is planning an after-hours cut to complete the repair.  This, too, he hopes to have completed by the end of next week.
              
MCI :  Quentin didn’t show today.

INDOT:  INDOT didn’t have any questions or concerns.

Stakeholder Questions:
Memorial Hospital: Larry didn’t have any new concerns.  He did note that he plans to have the locations of the hospital’s new signage marked in the near future so that any potential conflicts between sign placement and utility location can be avoided.

10:00 am 10:10 Break Utility and Stakeholders can leave

Submittals (List at Meeting):
1.                Type C Asphalt
2.                Tree Grate
I forwarded the submittals for each of these items on to Roger.  He plans to review these soon after today’s meeting so that they can be forwarded on to Rieth-Riley.


Action Items
1.      Madison Oyster Bar: Plumbing work on the vault at the Oyster Bar should be completed today.  This being the last utility, that leaves just the construction of the wall needed so that work on this section of Main Street can begin.  Tony hasn’t been given a specific date from Ziolkowski as to when construction of the wall is set to begin.

2.      Drive at Saigon/Colfax Structure: The topographical survey data has been sent to Structure Point.  Roger instructed Kevin to call daily to avoid idly waiting for a design for the new approach.

3.      Signal changes 10 intersections/Rieth-Riley prices:  Rieth-Riley submitted the prices to the City and they are still under review.  An answer should be coming today.

4.      Removals/trees/crosswalks/ eastside of Main:  Regarding the removals of trees, Rieth-Riley was asked to have Indiana Earth remove the entire tree at the same time as all other removals are taking place.  Further, the construction of temporary crosswalks needs to be prioritized as more and more intersections are being removed.  Tony was asked to try to get a hold of more “Sidewalk Closed Ahead” signs to keep pedestrian traffic safe.  Finally, Tony noted that removals on the east side of Main could begin as early as late next week.

5.      Sign Structure on Michigan:  Rich has been in contact with Pat about what the City needs.  He hasn’t looked to see if anything has yet been done, but he did note that he would remind Pat if need be.

6.      Updated Schedule: Scott relayed that he has been waiting to update the schedule until a decision is reached regarding the signal changes.

                                      
Reith Riley Construction Concerns/Questions:
·        Tony mentioned a concern regarding the brick pavers that were to be salvaged following the work InfraSource completed on the east side of Main between Washington and Jefferson Streets.  Toy decided that the burden will be on NIPSCO/InfraSource to clean the pavers and to remove the flowable fill used to cover their trench since the fill is much harder than it was planned to be.
·        As Pemberton moves forward, Toy would like to change all intersections in the downtown area to a four-way stop.  Regarding the controller and cabinet changes that might take place, no specific plans have been laid out, but Roger noted that the cabinets/controllers that lie on the state road will be changed to the bare minimum.  It was also brought to light that item #379 lacks a special provision detailing what all it entails.  As a result, it is more or less a useless item that needs to be looked into further.

City Concerns/Questions:
·        Toy talked with Larry briefly about Larson-Danielson attempting to use the parking lane on the east side of Lafayette between Navarre and Bartlett Streets.  Toy isn’t fond of the idea, because the contractor hasn’t been limiting its use of Lafayette to just the parking lane on the east side.

·        Regarding the patching table laid out in the plans, Roger noted that the locations listed on the patching table are not exact locations.  He’d like to see an inspector walk the job between Ewing and Sample to locate and list the specific areas that patching does need to be done.



7-7-16

Controlling Operation Bartlett: Wall Construction
Controlling Operation Marion: PCCP Pavement
Controlling Operation Lasalle to Ewing: Storm Pipework
Fraction of Day workable 10/10
Hi 84 Lo 69
Weather Am Overcast and Humid  PM Overcast and Humid

Rieth-Riley had a grading crew that finished grading the intersection of Bronson and Main in the morning. This section is now ready for concrete pavement.

Rieth-Riley also had a concrete crew pouring sidewalk and curb ramps on Michigan north of the Bartlett roundabout, and a curb crew pouring curb at the intersection of Main and Madison and on Main St. between Madison and LaSalle.

Ziolkowski had a 5 man crew making final formwork preparations for the concrete walls in the Bartlett roundabout which are scheduled to be poured tomorrow (7/8).

Woodruff had a crew installing storm pipe and structures on the west side of the intersection of Main and Jefferson. Jefferson is closed to traffic but Wayne street is now back open.

Indiana Earth had a crew removing curb and sidewalk on the south side of South St. for the construction of the Transpo approach. A second Indiana Earth crew removed curb and sidewalk along the west side of St. Joe between Washington and Colfax.