4-10-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy Rain  PM Cloudy Rain 
Hi 74 Lo 52

Reith Riley had a 9 man concrete crew pour the South West and South east corners of South Street and Michigan. once the concrete was poured a brief rain came and they had to refinish the side walk. They then moved to the South west corner of Washington and MLK and the South East Corner of MLK.

Reith Riley had a second crew working on the brick and stone on the South West corner of Main and Washington. 

Wisco worked on the east side of MLK between LaSalle and Colfax with a 5 man crew 

Pemberton Davis worked on the intersection of Wayne and MLK placing conduit and foundations on the North West, North East and South East corners. They also worked on the South West corner of Western and MLK.

4-7-2017

1pm, sunny 44deg

Rieth-Riley Conc Crew 8ppl; 
-Cycle Track outside of Finnies.
-NE cor of western &Main.
-NE & NW COR Mich & South
-


Rieth-Riley prep crew; brooming stone over brick pavers. 
NW cor of Monroe &Main grading.

Pemberton Davis; 

WISSCO working on irrigation on MLK between LaSalle and Colfax.

4-6-17

7:30am 36deg, Drizzle/Snow
Pemberton Davis - installing signal pole at Northwest corner of Main and Colfax.
Rieth-Riley not working.

4-5-17

11am 42deg Rain
Rieth-Riley Phil V. sawcut joints at NW corner of Main and Western & by TCU then left for the day.
NO OTHER WORK.

4-4-17

7:30am Rain 43deg
1:30pm Drizzle 44deg
Rieth-Riley Conc Crew 8ppl; poured SW Cor Main &Washington fill in area around traffic controller, Also SE Cor fill in area in front of TCU near AT&T vault. Poured ramps at NW Cor of Main&Western.
Rieth-Riley prep crew; NW Cor Main&Western.
Pemberton Davis; SE Cor Main&Jeff mole'ing for DH's.  NW Corner Main and Colfax wiring new signal base foundation.
Poured traffic controller base Southeast corner of Main and Monroe.
WISSCO working on irrigation on MLK between LaSalle and Colfax.

3-31-17

8 RR CREW
1 RR conc crew poured ramp at Southeast Corner Main and Western.


Pemberton installing light poles on the west side of Michigan north of Park St.
Also working at MLK and Colfax, removed controller cabinet on south east corner.

4/3/17

8am 47deg light rain/drizzle
12pm 50 deg, drizzle on and off.
Pemberton at Colfax & MLK wiring street lights. & Colfax & Main, poured new base & reworking conduit for new base (anchor bolts came in today).
1 conc. crew, 8ppl. Rieth-Riley working on curb around ramps at Western & Main (NW Cor.)
Grade Crew- at SE Cor Wash&MLK.
Brick Paver Crew- placing/sweeping fines into brick pavers.