Wednesday, February 22, 2017

2-21-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy Rain PM Cloudy Rain
Hi 62 Lo 38

Pemberton Davis had a crew working on pulling wire on the street lights on Main Street and Michigan from LaSalle to Marion. the crew went home after 4 hours due to the rain.

Tuesday 2-21-17
    MLK lighting; pulled in more #4 and #6 lighting cable and spliced poles. 
    Main St.; set handicap signs. 

Then we were rained out. 


No other work took place today.

Monday, February 20, 2017

2-20-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Sunny PM Sunny   
Hi 62 Lo 38

Pemberton Davis worked on setting the last of the street  lights North of LaSalle on Michigan and on Main they are going to work on pulling wire to the street lights.  

From Pemberton: 
Monday 2-20-17
   MLK and LaSalle; set light poles and conduit runs on north side. 
   MLK lighting; installing lightning cable south of LaSalle. 
   Main St. Lighting; set light pole at church. 
   Bartlett St.; reset signs at St. Joseph St. 

Friday, February 17, 2017

2-17-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Sunny PM Sunny   
Hi 50 Lo 30

Pemberton Davis is working on the walk/Waits at the corner of Jefferson,Washington and Wayne on Main Street. 

State Barricade is removing the Message Boards on Colfax and at the intersection of Saint Joe and South Street.

Phil @ Pemberton; "Main St. Lighting; spliced poles on east side north of Wayne St.   
Main St. Signals ; installed pedestrian signals and push buttons at several intersections. Washington, Jefferson,and Wayne St.   
Main and LaSalle; set a 12' pedestal pole on SE corner."

Thursday, February 16, 2017

2-16-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy Sunny PM Mostly Sunny   
Hi 39 Lo 30

Pemberton Davis worked on the street lights on Main Street from Marion to LaSalle. They also worked on the signage in the same area along with the bollard lighting. 

No other work took place.



Phil @ Pemberton; "MLK Blvd lightning; dig and poured base north of LaSalle. 
Main St. Lighting; removed existing foundation in front of church, dug and poured new foundation just south of that one. 
Main and LaSalle; dug and poured an pedestal foundation on SE corner." 

Wednesday, February 15, 2017

2-15-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy light snow PM partly Sunny   
Hi 38 Lo 30

Pemberton Davis worked on setting street light poles on Main Street from Marion to LaSalle. They also worked on placing signs on  Main Street and Michigan from Bartlett to LaSalle.

No other work took place today.

Phil @ Pemberton; "Main St. Lighting; installed light poles north of LaSalle. 
MLK Blvd signs ; set signs north of LaSalle to Navarre. Removed several signs as well." 

Tuesday, February 14, 2017

2-14-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Sunny PM Sunny   
Hi 45 Lo 30

Pemberton Davis put up street lights on Michigan from LaSalle to Marion and then moved to Main street and started working on Street lights from Marion to main. 

Reith Riley worked on Snow plow markers on Saint Joe street. 

No other work took place today.

Phil @ Pemberton; "MLK Blvd lighting; set light poles north of La Salle to roundabout. 
Main St. Signals ; set 12' pedestal poles at several locations, NE- Washington, NE- Jefferson, NE- Wayne."

Monday, February 13, 2017

2-13-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Sunny PM Sunny   
Hi 42 Lo 28

Pemberton Davis worked on placing  street lights on the east and west side of Saint Joe between Colfax and LaSalle. They also worked on the walk waits for Bronson and Main. They also worked on the street lights North of LaSalle on Michigan.

Reith Riley worked on the last of the snow plow markers on saint Joe street.

No other work took place today.